Information for Teesside Energy from Waste Plant, Haverton Hill Road, Billingham, Teesside
Status: ExistingPlanning Region: North East
Planning Sub-Region: Tees Valley Unitary Authority
Operator: SITA Tees Valley Limited (Suez Environment , formerly SITA) [See annual report]
Capacity: 390,000
Campaign Group(s): Contact coordinator@ukwin.org.uk to be put in touch with those opposing this development.
Notes: Capacity increased in 2009 [Source]. "Facility was extended from the original two line plant to a three stream plant in 2009 and now has a combined processing capacity of 390,000 tonnes of municipal waste per year" [Source]. Not to be confused with Sita’s ’North East Energy Recovery Centre’ next door. (Entry updated 2019-06-06)
Initial applications received for R1 status: 14 July 2020 (Environment Agency)
Uses data from https://environment.data.gov.uk/portalstg/home/item.html?id=e9c43501928740f1a9cab6e5ca651dfb/a> released by the Environment Agency under the Open Government License
Permit | Operator | Installation name | Installation address | Permit status | Waste input (000s tonnes per annum) | Incinerator type | Calculated R1 value | Application R1 status granted | Source of data used in R1 calculations | Date R1 application status granted |
---|---|---|---|---|---|---|---|---|---|---|
VP3034SG | Sita Tees Valley Ltd | North East Energy recovery Centre. Lines 1&2 | Teesside energy from Waste Plant, Haverton Hill Road, BILLINGHAM, Cleveland, TS23 1PY, | Permit issued | 195 | Municipal waste | 0.66 | Yes | Operational | 23/03/2015 |
VP3034SG | Sita Tees Valley Ltd | North East Energy recovery Centre. Lines 4 & 5 | Teesside energy from Waste Plant, Haverton Hill Road, Billingham, Cleveland, TS23 1PY, | Permit issued | 300 | Municipal waste | 0.7 | Yes | Design | 20/08/2013 |
VP3034SG | SITA Tees Valley Limited | Billingham Energy from Waste Plant – Line 3 | Teesside energy from Waste Plant, Haverton Hill Road, BILLINGHAM, Cleveland, TS23 1PY, | Permit issued | 128 | Municipal waste | 0.68 | Yes | Operational | 24/06/2015 |
Waste management for England 2019: Operational (Environment Agency)
Uses data from Waste Data Interrogator 2019 - 2019 Waste Summary Tables for England - Version 3 released by the Environment Agency under the Open Government License
Permit | Date First Permitted | Operator Name | Site Name | Site Address | Former Planning Region | Former Planning Sub-Region | EA Area | Type | Permitted Capacity (tonnage) | Tonnage Incinerated in 2006 | Tonnage Incinerated in 2007 | Tonnage Incinerated in 2008 | Tonnage Incinerated in 2009 | Tonnage Incinerated in 2010 | Tonnage Incinerated in 2011 | Tonnage Incinerated in 2012 | Tonnage Incinerated in 2013 | Tonnage Incinerated in 2014 | Tonnage Incinerated in 2015 | Tonnage Incinerated in 2016 | Tonnage Incinerated in 2017 | Tonnage Incinerated in 2018 | Tonnage Incinerated in 2019 | Comment |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
VP3034SG | 02/12/2005 | SUEZ Recycling and Recovery Tees Valley Ltd | Teesside EFW Plant | Teesside energy from Waste Plant,Haverton Hill Road,BILLINGHAM,Cleveland TS23 1PY | North East | Tees Valley Unitary Authorities | Northumberland Durham and Tees | Municipal and/or Industrial & Commercial | 756,000 | 216,737 | 206,427 | 204,327 | 256,609 | 295,816 | 217,706 | 337,380 | 349,454 | 644,099 | 594,981 | 600,160 | 563,349 | 637,270 | 654,003 |
Environment Agency 2018 Pollution Inventory: Substances
Uses data from the Pollution Inventory 2018 released by the Environment Agency under a special license
Permit | EA AREA NAME | ROUTE NAME | SUBSTANCE NAME | REPORTING THRESHOLD (kg) | QUANTITY RELEASED (kg) | REGULATED INDUSTRY SECTOR | REGULATED INDUSTRY SUB SECTOR |
---|---|---|---|---|---|---|---|
VP3034SG | North East | Air | Ammonia | 1000 | 6,675.80 | EfW | EfW |
VP3034SG | North East | Air | Nitrogen oxides (NO and NO2) as NO2 | 100000 | 602,857.00 | EfW | EfW |
VP3034SG | North East | Air | Arsenic | 1 | 2.9 | EfW | EfW |
VP3034SG | North East | Air | Cadmium | 1 | 3.6 | EfW | EfW |
VP3034SG | North East | Air | Chromium | 10 | 25.97 | EfW | EfW |
VP3034SG | North East | Air | Copper | 10 | 37.6 | EfW | EfW |
VP3034SG | North East | Air | Mercury | 1 | 2.69 | EfW | EfW |
VP3034SG | North East | Air | Nickel | 10 | 14.68 | EfW | EfW |
VP3034SG | North East | Air | Chlorine and inorganic chlorine compounds - as HCl | 10000 | 19,065.71 | EfW | EfW |
VP3034SG | North East | Air | Dioxins and furans (PCDDs/PCDFs) - as ITEQ | 0.00001 | 0 | EfW | EfW |
VP3034SG | North East | Air | Dioxins and furans (PCDDs/PCDFs) - as WHO TEQ | 0.00001 | 0 | EfW | EfW |
VP3034SG | North East | Air | Carbon dioxide | 10000000 | 637,270,300.00 | EfW | EfW |
Entry on WikiWaste:
https://wikiwaste.org.uk/index.php?title=Teeside_EfW_-_lines_1-5_(Teeside_%26_NEERC),_Billingham._line_3Information for North East Energy Recovery Centre (NEERC), Haverton Hill Road, Billingham, Stockton
Status: ExistingPlanning Region: North East
Planning Sub-Region: Teesside
Operator: Suez Environment (formerly SITA)
Capacity: 256,000
Campaign Group(s): Contact coordinator@ukwin.org.uk to be put in touch with those opposing this development.
Notes: Became operational in April 2014 [Source]. Expected to take waste from Durham County Council as part of an 8-year contract to handle 140,000 tonnes of household waste [Source]. Not to be confused with the existing 260,000 tpa Haverton Hill facility and its 130,000 tpa expansion. (Entry updated 2014-05-23)
Entry on WikiWaste:
https://wikiwaste.org.uk/index.php?title=North_East_Energy_Recovery_Centre._Lines_4_%26_5Annual Performance Report files:
60-AnnualPerformanceReport-2018.pdf60-AnnualPerformanceReport-2019.pdf
UKWIN (and therefore the UKWIN map) focuses on Municipal Waste Incinerators, whereas our colleagues at Biofuelwatch focus on biomass projects. If you are interested in waste wood or dedicated biomass incinerators then please see the Biofuelwatch map of UK Biomass Power Stations.
Please be aware: There is always room for improvement, so please send updates to coordinator@ukwin.org.uk. Existing Incinerator means a facility that is operational or under construction/commissioning. A Potential Incinerator is a facility where there is a proposal for an incinerator (e.g. planning application or planning consent) or other reason to believe an incinerator might be built/proposed in the future. A Prevented Incinerator is something which used to be a proposal or expected incinerator which we do not believe is currently being progressed (e.g. because the project was cancelled, planning permission refused, or years have gone by since the permission was granted without any progress) - in some cases a facility marked as prevented is being progressed without us being aware or is subsequently revived. Capacity is usually the permitted or maximum advertised capacity of the facility.