Menu Close

Incinerator information library

Information for Redcar Energy Centre, Site of Redcar Bulk Terminal, Redcar

Status: Potential
Planning Region: North East
Planning Sub-Region: Redcar and Cleveland
Operator: Partnership betweem Low Carbon and PMAC Energy
Capacity: 500,000 (RDF)
Campaign Group(s): Contact coordinator@ukwin.org.uk to be put in touch with those opposing this development
Notes: In July 2022 it was reported that the facility was awarded Contracts for Difference support [Source]. Project announced in July 2018 [Source]. Planning permission was granted in January 2021 and is set for completition in 2025 [R/2020/0411/FFM, Source]. Permit issued in May 2025 (EPR/TP3502MS/A001). In ealy 2026 an Environmnet Agency Compliance Assessment Report (CAR) reported that: "The site is still awaiting construction. The operator advised [that] the project is in an advanced stage of development but the next step of selecting project partners will take place over the next 12-18 months". (Entry updated 2026-03-03)

Permit files:

244-Permit-2025.pdf

Permit Decision files:

244-PermitDecision-2025.pdf

Planning Consent files:

244-PlanningConsent-2021.pdf

Environment Agency Compliance Assessment Reports

Click here to see the incinerator compliance documents for existing English incinerators

Standard notice:

UKWIN (and therefore the UKWIN map) focuses on Municipal Waste Incinerators, whereas our colleagues at Biofuelwatch focus on biomass projects. If you are interested in biomass incinerators (including waste wood plants) over 20MW then please see the Biofuelwatch map of UK Biomass Power Stations. Those concerned about biomass plants, including waste wood plants, should email Biofuelwatch at biofuelwatch[at]gmail.com.

Please be aware: There is always room for improvement, so please send updates to coordinator@ukwin.org.uk. Existing Incinerator means a facility that is operational or under construction/commissioning. A Potential Incinerator is a facility where there is a proposal for an incinerator (e.g. planning application or planning consent) or other reason to believe an incinerator might be built/proposed in the future. A Prevented Incinerator is something which used to be a proposal or expected incinerator which we do not believe is currently being progressed (e.g. because the project was cancelled, planning permission refused, or years have gone by since the permission was granted without any progress) - in some cases a facility marked as prevented is being progressed without us being aware or is subsequently revived. Capacity is usually the permitted or maximum advertised capacity of the facility.