Incinerator information library

Information for New Barnfield, Hatfield

Status: Prevented
Planning Region: East of England
Planning Sub-Region: Hertfordshire
Operator: Veolia Environmental Services
Capacity: 380,000
Campaign Group(s): Hatfield Anti Incineration (HAI) and Herts WOW! (WithOut Waste) (a network of groups including North Herts Friends of the Earth, Welwyn Hatfield FOE, N Herts Green Party, Welwyn Hatfield Green Party and Transition Town Letchworth)
Notes: The Secretary of State refused planning consent for the proposal in June 2014 [Source], but this decision was quashed by a legal challenge brought by Veolia. Following a re-determination, the application was refused again in July 2015 and Veolia announced in August 2015 that they were not challenging this decision [Source, Source]. PFI was funding was withdrawn in October 2014 [Source]. Veolia awarded Hertfordshire County Council waste PFI contract in April 2011 [Source]. The proposed facility was intended to process both C&I and LACW waste. It was reported in February 2025 that the council intends to put the incinerator site up for sale because the council had no further plans for that site [Source]. (Entry updated 2025-03-10)

R1 status of incinerators - 8 April 2026 (Environment Agency)

Uses data from R1 status of incinerators in England released by the Environment Agency. © Environment Agency copyright and/or database right 2026. All rights reserved.

Permit: MP3637FL

OperatorInstallation nameInstallation addressPermit statusWaste input (000s tonnes per annum)Incinerator typeCalculated R1 valueApplication R1 status grantedSource of data used in R1 calculationsDate R1 application status granted
Veolia ES Hertfordshire LtdNew Barnfield Recycling and Energy Recovery FacilityNew Barnfield, Travellers Lane, Hatfield, Hertfordshire, AL10 8XGPermit surrendered352Municipal waste0.72YesDesign11/06/2012

Environment Agency Compliance Assessment Reports

Click here to see the incinerator compliance documents for existing English incinerators

Standard notice:

UKWIN (and therefore the UKWIN map) focuses on Municipal Waste Incinerators, whereas our colleagues at Biofuelwatch focus on biomass projects. If you are interested in biomass incinerators (including waste wood plants) over 20MW then please see the Biofuelwatch map of UK Biomass Power Stations. Those concerned about biomass plants, including waste wood plants, should email Biofuelwatch at biofuelwatch[at]gmail.com.

Please be aware: There is always room for improvement, so please send updates to coordinator@ukwin.org.uk. Existing Incinerator means a facility that is operational or under construction/commissioning. A Potential Incinerator is a facility where there is a proposal for an incinerator (e.g. planning application or planning consent) or other reason to believe an incinerator might be built/proposed in the future. A Prevented Incinerator is something which used to be a proposal or expected incinerator which we do not believe is currently being progressed (e.g. because the project was cancelled, planning permission refused, or years have gone by since the permission was granted without any progress) - in some cases a facility marked as prevented is being progressed without us being aware or is subsequently revived. Capacity is usually the permitted or maximum advertised capacity of the facility.