Information for Portland Port, Castletown

Status: Potential
Planning Region: South West
Planning Sub-Region: Dorset
Operator: Powerfuel Portland
Capacity: 202,000 (RDF)
Campaign Group(s): Stop Portland Waste Incinerator, The Portland Association, Jurassic Coast Incinerator Action Group and Coalition Against The Burner
Notes: Planning permission granted on appeal in September 2024 (APP/D1265/W/23/3327692), and in October 2024 it announced that legal challenge had been issued by a local campaigner [Source]. A legal challenge against the grant of planning permission is ongoing as of July 2025 with a hearing expected by Spring 2026. Plans for the incinerator intended to burn RDF were announced in November 2019 [Source, Source]. Planning application was submitted in September 2020 [See application ref WP/20/00692/DCC]. In March 2023 the Dorset council voted unanimously to refuse planning permission WP/20/00692/DCC (See video recording). Environmental permit AP3304SZ was issued in February 2025. On 5th November the Environment Agency opened a consultation on a variation to the permit that would increase the number of waste codes that could be incinerated, with the consultation closing on 18 December 2025 [EPR/AP3304SZ/V002]. In June 2026 the Environment Agency published their draft decision document and draft permit variation which were subject to consultation through to the end of July, although the EA may accept late submissions (EPR/AP3304SZ/V002). (Entry updated 2026-08-18)

Plume Plotter entry for Portland


This pollution prediction was produced by Plume Plotter. Click here for more details.

R1 status of incinerators - 8 April 2026 (Environment Agency)

Uses data from R1 status of incinerators in England released by the Environment Agency. © Environment Agency copyright and/or database right 2026. All rights reserved.

Permit: AP3304SZ

OperatorInstallation nameInstallation addressPermit statusWaste input (000s tonnes per annum)Incinerator typeCalculated R1 valueApplication R1 status grantedSource of data used in R1 calculationsDate R1 application status granted
Powerfuel Portland LtdPortland Energy Recovery FacilityIncline Road, Portland, DT5 1DBPermit issued183Municipal waste0.76YesDesign26/02/2024

Objection files:

259-Objection-from-UKWIN-February-2021.pdf
259-Objection-from-UKWIN-September-2021.pdf.pdf

Permit files:

259-Permit-2025.pdf

Permit Decision files:

259-PermitDecision-2025.pdf

Planning Consent files:

259-PlanningConsent-2024.pdf

Planning Refusal files:

259-PlanningRefusal-2023.pdf

Environment Agency Compliance Assessment Reports

View compliance documents for this incinerator
View the full UKWIN incinerator compliance index

Historic permit-related documents

See historic documents relating to permit AP3304SZ

Standard notice:

UKWIN (and therefore the UKWIN map) focuses on Municipal Waste Incinerators, whereas our colleagues at Biofuelwatch focus on biomass projects. If you are interested in biomass incinerators (including waste wood plants) over 20MW then please see the Biofuelwatch map of UK Biomass Power Stations. Those concerned about biomass plants, including waste wood plants, should email Biofuelwatch at biofuelwatch[at]gmail.com.

Please be aware: There is always room for improvement, so please send updates to coordinator@ukwin.org.uk. Existing Incinerator means a facility that is operational or under construction/commissioning. A Potential Incinerator is a facility where there is a proposal for an incinerator (e.g. planning application or planning consent) or other reason to believe an incinerator might be built/proposed in the future. A Prevented Incinerator is something which used to be a proposal or expected incinerator which we do not believe is currently being progressed (e.g. because the project was cancelled, planning permission refused, or years have gone by since the permission was granted without any progress) - in some cases a facility marked as prevented is being progressed without us being aware or is subsequently revived. Capacity is usually the permitted or maximum advertised capacity of the facility.