Information for Shepperton Eco Park, Charlton Lane, Shepperton

Status: Existing
Planning Region: South East
Planning Sub-Region: Surrey
Operator: Suez Environment (formerly SITA)
Capacity: 60,000
Campaign Group(s): Spelthorne Against The Eco-Park (SATEP) and Capel Action Group
Notes: Listed as under construction as of May 2015 in BEIS database [Source]. In June 2018 it was reported that comissioning was due to begin late Summer 2018 [Source]. Planning permission granted in August 2014 (ref SP13/01553/SCC, and amended proposal approved September 2014 [Source, Source]. It was reported in July 2013 that planning permission was being sought for an RDF-fed fluidised-bed gasification-type incinerator [Source, Source]. New technology supplier chosen as Ascot Environmental were forced into administration on the 18th of May 2012, rendering the previous planning consent and contract out of date [Source, Source]. A series of amendments were approved in March 2017 (ref: SP13/01153/SCA1). (Entry updated 2018-07-26)

Plume Plotter entry for Shepperton_ge


This pollution prediction was produced by Plume Plotter. Click here for more details.

Waste management for England 2018: Non-operational (Environment Agency)

Uses data from Waste Data Interrogator 2018 - 2018 Waste Summary Tables for England - Version 2 released by the Environment Agency under the Open Government License

PermitOperator NameSite NameSite AddressFormer Planning RegionFormer Planning Sub-RegionEA AreaTypePermitted Capacity (tonnes)Comment
VP3997NKSUEZ Recycling and Recovery Surrey LtdCharlton Lane Eco ParkCharlton Lane Eco Park,Charlton Lane,Sunbury,Surrey TW17 8QASouth EastSurreyHertfordshire and North LondonMunicipal and/or Industrial & Commercial60,000Permitted in 2012. Not yet operational

Entry on WikiWaste:

https://wikiwaste.org.uk/index.php?title=Charlton_Lane_Eco_Park_(ACT)

UKWIN (and therefore the UKWIN map) focuses on Municipal Waste Incinerators, whereas our colleagues at Biofuelwatch focus on biomass projects. If you are interested in waste wood or dedicated biomass incinerators then please see the Biofuelwatch map of UK Biomass Power Stations.

Please be aware: There is always room for improvement, so please send updates to coordinator@ukwin.org.uk. Existing Incinerator means a facility that is operational or under construction/commissioning. A Potential Incinerator is a facility where there is a proposal for an incinerator (e.g. planning application or planning consent) or other reason to believe an incinerator might be built/proposed in the future. A Prevented Incinerator is something which used to be a proposal or expected incinerator which we do not believe is currently being progressed (e.g. because the project was cancelled, planning permission refused, or years have gone by since the permission was granted without any progress) - in some cases a facility marked as prevented is being progressed without us being aware or is subsequently revived. Capacity is usually the permitted or maximum advertised capacity of the facility.