Notes: Construction began in July 2015 and it was reported in July 2018 that the site was in commissioning and that the facility was expected to be operational in August 2018 [Source, Source]. In July 2019 there was a fire at the incinerator's waste storage unit [Source]. Granted planning permission in August 2013 [Source]. A long-term municipal waste management contract was signed between Viridor and the South London Waste Partnership in November 2012 [Source]. Croydon Council led the procurement process for the South London Waste Partnership (SLWP), which also includes the boroughs of Sutton, Merton and Kingston. On the 20th of October 2010 the Government withdraw PFI funding for the project [Source]. (Entry updated 2019-11-22)

Plume Plotter entry for Southlondon


This pollution prediction was produced by Plume Plotter. Click here for more details.

Waste management for England 2018: Operational (Environment Agency)

Uses data from Waste Data Interrogator 2018 - 2018 Waste Summary Tables for England - Version 2 released by the Environment Agency under the Open Government License

PermitDate PermittedOperator NameSite NameSite AddressFormer Planning RegionFormer Planning Sub-RegionEA AreaTypePermitted Capacity (tonnage)Tonnage Incinerated in 2006Tonnage Incinerated in 2007Tonnage Incinerated in 2008Tonnage Incinerated in 2009Tonnage Incinerated in 2010Tonnage Incinerated in 2011Tonnage Incinerated in 2012Tonnage Incinerated in 2013Tonnage Incinerated in 2014Tonnage Incinerated in 2015Tonnage Incinerated in 2016Tonnage Incinerated in 2017Tonnage Incinerated in 2018Comment
TP3836CT23/07/20134Evergreen Technologies LimitedKemsley Park EfWKemsley Park,Sittingbourne,Kent, ME10 2feSouth EastKentKent and South LondonMunicipal and/or Industrial & Commercial302,500------------80,316

Environment Agency 2018 Pollution Inventory: Substances

Uses data from the Pollution Inventory 2018 released by the Environment Agency under a special license

PermitEA AREA NAMEROUTE NAMESUBSTANCE NAMEREPORTING THRESHOLD (kg)QUANTITY RELEASED (kg)REGULATED INDUSTRY SECTORREGULATED INDUSTRY SUB SECTOR
TP3836CTKent, South London and East SussexAirCarbon dioxide1000000021,529,266.00EfWEfW

Entry on WikiWaste:

https://wikiwaste.org.uk/index.php?title=Beddington_EfW

Annual Performance Report files:

51-AnnualPerformanceReport-2018.pdf
51-AnnualPerformanceReport-2019.xlsm

Permit files:

51-Permit-2013.pdf

UKWIN (and therefore the UKWIN map) focuses on Municipal Waste Incinerators, whereas our colleagues at Biofuelwatch focus on biomass projects. If you are interested in waste wood or dedicated biomass incinerators then please see the Biofuelwatch map of UK Biomass Power Stations.

Please be aware: There is always room for improvement, so please send updates to coordinator@ukwin.org.uk. Existing Incinerator means a facility that is operational or under construction/commissioning. A Potential Incinerator is a facility where there is a proposal for an incinerator (e.g. planning application or planning consent) or other reason to believe an incinerator might be built/proposed in the future. A Prevented Incinerator is something which used to be a proposal or expected incinerator which we do not believe is currently being progressed (e.g. because the project was cancelled, planning permission refused, or years have gone by since the permission was granted without any progress) - in some cases a facility marked as prevented is being progressed without us being aware or is subsequently revived. Capacity is usually the permitted or maximum advertised capacity of the facility.